WORK PROJECTS AT COMPLEX

3/22/19:
From what I know as of today from Management is that there will be lanai spalling work performed some time in September on 16 units complex wide.  Not sure of what units nor when, except for the only unit of ours that we know of will be down some time in September is #239.  Dates still pending.  There will be scaffolding erected on the affected unit lanais and can be some loud noise during the day (9am-5pm Monday thru Friday) while they remove the compromised concrete.  The whole project will take 5 to 6 weeks and more information will be known in the coming weeks.  

UPDATE (4/24/19; email from GM):

Aloha Islander Owners,

 

This is to notify all owners that spalling issues have been discovered and must be repaired on approximately 15 to 20 lanais around the property.  The affected lanais are located in the Niihau, Oahu, Molokai and Kauai buildings.  This type of repair work will require specific units in these buildings to be closed at various times during a five week period beginning on September 9, 2019 through October 11, 2019.   Please note that the duration of this repair project is an estimate and could be extended depending on weather and the severity of the repair.  A separate letter with more details will be sent to the owners with units in the affected buildings.  However all owners should be aware that spalling work will be taking place during this time period.  Therefore, activity, dust and noise levels will be higher than normal on property.

 

 

Units affected during this project are (only three KrellersGetaway units directly affected in red):  


Niihau Building:  145, 147, 149, 153, 245, 247, 249, 345, 353 (work on this building commencing September 9)



Oahu Building:  139, 144, 239, 244, 344 (work on this building commencing September 23)



Molokai Building:  164, 264 (work on this building commencing September 23)



Kauai Building:  123, 124, 126, 127, 128, 130, 223, 224, 226, 227, 228, 230, 324, 326, 330 (work on this building commencing September 30)



From what we understand, the extent of the work and noise/disturbance is unknown and won't be determined until the affected areas are opened up and examined.





4/24/19
Painting of buildings (each side of building)

Here is a list of tentative dates (weather dependent) we just received for management.  From what we understand, the noise is minimal, but there will be scaffolding erected on each side of the building so painters can get to 2nd and 3rd floor, corner, units.  The ends of the buildings are the only affected units and the work schedule is Monday thru Friday from 9 am - 5 pm.  We have listed our units that will be impacted by the painting project in that they will have scaffolding erected outside of their side view windows at some point during the project.

Hawaii 22 stack:  4/26 – 5/2

Lanai 38 stack:  5/3 - 5/9

Lobby 09/14 stack:  5/10 – 5/16

Hawaii 15 stack:  5/17 – 5/23  (#115)

Niihau 45 stack:  5/24 – 5/30  (#245 and #345)

Niihau 54 stack:  5/31 – 6/6  (#154 and #254)

Molokai 64 stack:  6/7 – 6/13

Molokai 55 stack:  6/14 – 6/20

Maui 72 stack:  6/21 – 6/27

Oahu 44 stack:  6/28 – 7/4

Oahu 39 stack:  7/5 – 7/11  (#239)

Maui 65 stack:  7/12 – 7/18

Lobby 00/04 stack:  7/19 – 7/25




Bike Path
 The Board continues to work with the County of Kauai on the bike path planning from the proposed easement between the Islander on the Beach and Kauai Shores to potential privacy fences and landscaping. The work is in the planning and design stages, with project start dates ranging from late 2016 to early 2017.

No updates to the Bike Path as of July 2017.

Comments